|
In
April, 1999, Nepal enacted the Arbitration Act, 1999, which came into
force at once. The principal object of the Act is to up-date the current
legal provisions relating to arbitration (as stated in the Preamble).
The Act borrows some propositions incorporated in the UNCITRAL Model
Law on the subject. But it does not blindly copy them. Besides this,
it tries to put, in simple language, the governing principles, without
a slavish imitation of the conservative style of drafting. A look at
some of its important provisions would be useful.
Arbitration
agreement
Arbitration
agreement is the foundation of arbitration under the Nepal Act. It must
be an agreement for the settlement (through arbitration) of any dispute
concerning any specific legal issue, arising under a contract or otherwise.
The Act avoids the vague words “defined legal relationship” occurring
in the UNCITRAL Model Law (and in the Indian Act of 1996). It is clarified
that letters, telex, telegrams or telefax messages, or any other similar
messages “whose records can be maintained in a written form” can form
an arbitration agreement. Not raising an objection to the other party’s
claim for reference to arbitration also amounts to arbitration agreement
[section 2(a)].
Counter-claim
is expressly recognised, and so is a “Rejoinder” to a counter-claim
[section 2(f) and (g)]. Once there is an arbitration agreement in respect
of a dispute, then resort to arbitration is mandatory [section 3(I)].
Arbitration in a pending suit is permitted by agreement [sections 3(2)
and 4].
Arbitrators
and chief arbitrator
The
number of arbitrators can be determined by agreement, failing which,
it should ordinarily be three [section 5(1)].
If
an even number is provided for, then the arbitrators must choose an
additional arbitrator [section 5(2)]. Subject to agreement, the process
of appointing arbitrators must be started within 30 days from the date
when the “reason for the settlement of a dispute through arbitration
arises” [section 6(1)].
The
method of appointment is left to the agreement. Failing agreement, each
party shall appoint one arbitrator and the arbitrators so appointed
shall appoint a third arbitrator, who shall work as “chief arbitrator”
[section 6(2) to (4)].
The
concept of “chief arbitrator” is not to be found in the Indian Act of
1996. The “presiding arbitrator” mentioned in the Indian Act does not
have that status.
Under
the Nepal Act, where the agreement is silent about the appointment of
arbitrators or where no arbitrator can be appointed according to the
agreement, then a party may apply to the Appellate Court for appointing
three arbitrators (section 7).
Appropriate
provision is made for filling up of vacancies in the post of arbitrators
[section 8(1)]. Here also, the “Appellate Court” has a role to play,
if the parties fail to act [section 8(2)].
Oath
to be taken by arbitrators
The
Nepal Act contains an interesting provision (not usually found in Arbitration
Acts) requiring the arbitrator to take a written oath of impartiality
and honesty, for which a Form is provided in the Schedule. A copy is
to be sent to the Appellate Court. Any matters raising a reasonable
doubt about impartiality or independence of an arbitrator must be cleared
by the arbitrator before signing the oath (section 9).
Qualifications
A
very interesting provision, found in the Nepal Act, relates to the qualifications
of arbitrators. The following persons shall not be qualified for appointment
as arbitrators:
(a)
Those who are disqualified for entering into contracts under “current
law” – a phrase which pithily expresses the concept of “any law for
the time being in force”.
(b)
Those who have been punished by a court on criminal charges involving
a moral turpitude. This is a very interesting provision, not found in
most Arbitration Acts.
(c)
Those who have become insolvent or who have been declared bankrupt.
(d)
Those who have any personal interest in the dispute that is to be settled
through arbitration.
(e)
Those who do not possess the specific qualifications laid down in the
arbitration agreement (section 10).
Removal
of arbitrators
The
Nepal Arbitration Act contains a rather drastic provision, for the removal
of arbitrators. The matter can, of course, be dealt with by agreement.
But, failing that, the Act provides that a party may “apply” to the
arbitrator, requesting for permission to remove the arbitrator”.
[The
wording is a quaint but polite form of language. The gist seems to be,
that the arbitrator can be called upon to resign].
This
procedure can be resorted to, in the following circumstances:–
(a)
Where the arbitrator clearly shows bias instead of working in an impartial
manner.
(b)
Where the arbitrator engages in improper actions or commits fraud in
the course of arbitration.
(c)
“In case any arbitrator frequently commits mistakes or irregularities
in the arbitration proceedings”. [This is rather an extreme provision,
as “mistake” is a very wide word].
(d)
If the arbitrator does not attend meetings for more than three months,
without furnishing satisfactory reasons, in order to delay the proceedings
in an improper manner.
(e)
If the arbitrator takes any action opposed to the principle or rules
of natural justice.
(f)
If the arbitrator lacks the requisite qualifications or ceases to be
qualified.
The
arbitrator must take a decision (on the application to remove him) within
30 days. Against his decision, an appeal may be filed with the Appellate
Court, whose decision shall be final (section 11).
Venue
The
“office” of the arbitrator under the Nepal Act is to be located at the
place chosen by the parties. If the parties fail to agree, then the
office shall be at the place, specified by the arbitrator in the light
of all the circumstances. However, (unless the parties have made other
arrangement), the arbitrator may record the statements of witnesses,
obtain opinion of experts and inspect any document, object or place
at any other appropriate place (section 12).
Language
Language
of the arbitration proceedings shall be that chosen by the parties.
Failing such choice, it will be the language used in the agreement.
(section13). Claim,
“objection”, counter-claim and rejoinder
A
noteworthy feature of the Nepal Arbitration Act is the detailed provisions,
which it makes, regarding the claim, and subsequent pleadings of the
parties, and annexures thereto. The rather long provision in the Act
(section 14) can be summarised for the present purpose as under:
(a)
The claim must be made in writing, explicitly mentioning the details
of the subject matter of the dispute and the remedy sought, along with
the evidence. Copy is to be given to the other party.
(b)
To the claim so filed, the other party shall submit its “objection”
(defence).
(c)
The other party can, along with the “objection”, submit a counter-claim.
(d)
To the counter-claim, the claimant can file a “rejoinder” (with copy
to the opposite party) (section 14).
Time
limits for various pleadings and claims
The
Nepal Act also lays down time limits for filing the various categories
of claims mentioned above. Subject to an agreement between the parties
laying down a different time limit, these time limits are as under:
–
to be filed within three months from the date when the dispute arose
or when the arbitrator is appointed (whichever is later] ;
–
to be filed within thirty days from the date of receipt of the claim
;
–
same time limit as is mentioned in (b) above ;
–
to counter, claim to be filed within 15 days from date on which counter
claim is filed ;
The
arbitrator is empowered to extend the time limit for not more than seven
days (section 14).
Material
to accompany the pleadings
The
Nepal Act has a provision of considerable practical use, regarding the
material that should accompany the pleadings (i.e., claim, objection,
counter-claim or rejoinder). The following must be submitted along with
the pleadings:–
(a)
documents intended to be relied upon,
(b)
evidence substantiating the documents,
(c)
list of witnesses proposed to be produced. [section 1(5)].
Failure
to submit claims
If
there is failure to submit the claim within the prescribed time limit,
the arbitration proceedings “shall terminate” – unless the agreement
provides to the contrary. If there is failure to submit the “objection”
(i.e., the defence) within the specified time limits, then the arbitrator
must still proceed to determine the claim on the merits (section 15).
Challenge
to jurisdiction
The
Nepal Act contains a fairly elaborate provision as to the procedure
to be followed, where a party raises an objection:
(i)
that the arbitrator has no jurisdiction over the dispute referred to
him, or
(ii)
that the contract “because of which the dispute has emerged” is itself
illegal or null and void. Such
objection must be raised before expiry of the time limit laid down for
filing the defence to the main case.
Any
party not satisfied with the arbitrator’s decision on such an objection
may appeal to the Appellate Court within thirty days. The decision of
the Appellate Court is final. But the filing of the appeal shall not
be deemed to have prejudiced the power of the arbitrator to continue
his proceedings and to pronounce his decision before the petition is
finally disposed of by the court (section
16).
One
may be permitted to add here, that, generally, the question of the procedure
to be followed in respect of objections to jurisdiction is a vexing
one. The Indian Act of 1996 does not permit an interim appeal against
the decision of the arbitrator, rejecting the objection to jurisdiction.
The proceedings must go on, but the aggrieved party can raise the point
again, when he challenges the award before the competent court. [section
34, Arbitration and Conciliation Act, 1996 (India)].
The
position under the Nepal Act is somewhat different. An interim appeal
can be taken to the Appellate Court, as stated above. But the Nepal
Act also takes care to expressly provide that the proceedings must go
on, in the meantime. This is a good compromise; and whoever thought
of it, deserves the grateful compliments of the business community.
Of course, lovers of legalism are likely to argue that if the objection
to jurisdiction is ultimately allowed by the Appellate Court, then the
arbitration proceedings (which are allowed to be held in the meantime)
would become infructuous. This is theoretically true. But, in practice,
it is found that more often than not, the objections to jurisdiction
or to arbitrability are ill-founded (if not totally frivolous).
Working
procedure
The
Nepal Act deals with the procedure to be followed by the arbitrator,
as under:
(a)
The parties may, in the arbitration agreement, lay down the procedure.
Failing agreement, the procedure laid down in the Act shall be followed.
(b)
If, on a particular matter, the Act is silent, the arbitrator can seek
the consent of the parties consent on that matter.
If
the parties fail to reach an agreement on any procedural matter, the
procedure (in that respect) “shall be as prescribed by the arbitrator
himself” [Section 17(1)].
The
arbitrator must start the arbitration proceedings “immediately” after
receiving the pleadings [section 17(2)].
He
has to keep records of the proceedings in the case file. [section 17(3)].
Absence of one arbitrator
A
very useful provision in the Nepal Act deals with the absence of one
of the arbitrators at a particular hearing. It is provided that where
the dispute is referred to three or more arbitrators, the arbitrators
who are present may conduct all arbitration proceedings, other than
taking the final decision or issuing the final order [section 17(4)].
Ex
parte proceedings
It
is further provided in the Nepal Act that if any party does not present
itself at the arbitration proceedings after due notice, the arbitrator
may nevertheless continue the arbitration proceedings and pronounce
his decision on the basis of the available material [section 17(5)].
Conclusion
of the proceedings
On
completion of the hearing, the arbitrator has to issue an order that
the hearing has concluded. The Act lays down that “evidence may not
be examined or the parties heard thereafter [section 17(6)].
Award
Unless
the agreement provides otherwise, the arbitrator must read out his written
decision, within 30 days of the order closing the hearing. [section
17(7)]. This provision in the Nepal Act (as to reading out the award)
does not occur in the Indian Act of 1996. [See also “Award: time limit,
infra].
Hearing
in camera
The
Nepal Act expressly provides that the arbitration proceedings shall
be held in camera, unless the parties otherwise decide (Section 19).
Applicable
law
The
Nepal Act provides that the Nepal law shall be the substantive law applicable,
unless the agreement provides otherwise. But the arbitrator must settle
the dispute according to the “conditions stipulated in the concerned
contract” He has also to take into account the applicable commercial
usages (Section 18).
Bank
guarantee from foreigners
An
interesting provision found in the Nepal Act relates to foreigners.
If any of the parties is a foreigner, so that the decision pronounced
by the arbitrator is not likely to be implemented, then the arbitrator
has power to obtain a bank guarantee or other appropriate guarantee,
as prescribed by the arbitrator [Section 21(1)(d)].
Interim
orders
The
Nepal Act also confers on the arbitrator power to issue (on the request
of a party) preliminary orders or interim or provisional orders, in
respect of any matter connected with the dispute or to take a “conditional
decision” [Section 21(1)(g)]. The Act does not, however, elaborate this
provision. Case law on the subject has to be awaited.
Certified
copies
The
Nepal Act also confers on the arbitrator power to issue certified copies
[Section 21(1)(h)]. This is a very useful provision, as many documents
tend to be locked up before the arbitrator.
Appeal
Against
the various, interim orders issued by the arbitrator under section 21(1),
of the Nepal Act an appeal lies to the Appellate Court [Section 21(2)].
Equal
opportunity
The
Nepal Act provides that each party shall be provided with an equal and
adequate opportunity to present its case, “subject to this Act”. [section
22(1)]. With this, one may compare section 18 of the Indian Act of 1996,
which reads as under:
“18.
The parties shall be treated with equality and each party shall be given
a full opportunity to present his case.”
Two
points of difference may be noted:
(a)
The Indian Act contemplates “full opportunity”, while the Nepal Act
provides for “equal and adequate” opportunity. The Nepal wording is
preferable.
(b)
The Nepal Act makes the provision subject to the Act, which also is
more precise than the Indian provision.
Appearance
by the parties
Under
the Nepal Act, any party may attend the arbitration proceedings:–
(a)
either personally, or
(b)
by proxy, or
(c)
through legal practitioner, [Section 22(2)].
Court
assistance
Court
assistance may be requested by the arbitrator, to examine any evidence
concerning the dispute, (section
23).
Award:
time limit
The
Nepal Act does contain provisions regarding the time limit for pronouncing
the award, as under:
(a) Subject to agreement between the parties, the award must be pronounced
within 120 days from the date on which the process of submission of
pleadings is complete, (section 24).
(b)
However, this is subject to the provision (already noted above) in section
17(7), under which the award must be pronounced within 30 days of the
date on which the hearing is “closed” by a formal order, [Section 24,
read with section 17(7)]. [See “Award”, supra].
Majority
and minority decision
The
Nepal Act provides that where there are three or more arbitrators, the
decision of the majority prevails. But what about cases where there
is no majority view on a particular matter? This situation, not dealt
with specifically in the Indian Act of 1996, is specifically dealt with
in the Nepal Act. It provides that in such cases, the decision of the
chief arbitrator prevails.
It
may be recalled that the Nepal Act specifically contemplates the designation
of an arbitrator as, “chief arbitrator” under section 6(4). [See “Arbitrator’s
and chief arbitrator”, supra].
Finally,
the Nepal Act requires every arbitrator to sign the award. If there
is any special reason for his not signing, the other arbitrators, while
signing shall explicitly mention that fact. Dissent is, of course, allowed.
Contents
of the award
Subject
to a contrary provision in the agreement, the award under the Nepal
Act must give brief particulars of the matter referred to arbitration,
the grounds for deciding that the arbitrator had jurisdiction (where
such a point had been raised) and reasons for the decision, (section
27).
The
amount awarded and interest, etc. should be mentioned, (section 27).
The decision of the arbitrator has to be read out, (section 28).
Corrections
in the award
Correction
of arithmetical or clerical mistakes in the award is permitted, under
the Nepal Act. If
a point made in the claim has not been decided by the arbitrator, he
can be requested to do so, within the prescribed period, (Section 29).
Challenge
to the award
An
award may be challenged on a petition filed before the Appellate Court
within 35 days from receipt of a copy by the petitioner. The grounds
of challenge are as under:
(a)
Incompetence of a party to sign the agreement or invalidity of the agreement.
(b)
Notice of arbitration proceedings not given to the petitioner.
(c)
Decision has been rendered:
(i)
on a matter not referred to the arbitrator; or
(ii) in a manner contrary to the prescribed conditions; or
(iii) by acting beyond the arbitrator’s jurisdiction.
(d)
Procedure of designation of arbitrators or their functions and actions
do not conform to the agreement or the Act.
(e)
The matter is not arbitrable under the law of Nepal.
(f)
The award is likely to prove detrimental to the “public interests or
policies” (section 30).
Interest
In
a monetary award (subject to agreement to the contrary), award of interest
is compulsory under the Nepal Act. The interest is to be paid at the
rate prescribed by the arbitrator in the light of the nature of the
business connected with the dispute, ensuring that it is not higher
than the rate of interest currently charged by commercial banks in respect
of similar transactions (section 33).
Implementation
of the award
The
award is to be implemented by the District Court, under the Nepal Act
on a petition filed within 30 days from the date of expiry of the time
limit prescribed for implementing it. (The time limit is 45 days) (sections
31and 32).
Interest
not award
The
Nepal Act is silent as to the situation where the award itself is silent
about interest. The situation does not fall within the power of “correction”
conferred by section 29. In fact, section 29(1) expressly prohibits
review in points of substance.
It
would have been better if the Act had contained a provision that if
the award is silent on this point, then it shall be deemed to have awarded
interest at the rate of, say, 12 per cent per annum. The
date from which interest is to run, is also not mentioned in the Nepal
Act.
Conclusion
Notwithstanding
some minor omissions, the Nepal Arbitration Act of 1999 is likely to
prove an eminently workable measure. It has struck a compromise between
a doctrinnaire approach and a practical one. The grounds for setting
aside the award should, however, be made more narrow, by providing that
substantial injustice should be proved, before setting aside an award.
There should also be a provision that if the award is silent as to interest,
the interest shall run at 12 per cent per annum from the date on which
the cause of action arose.
|