IN THE SUPREME
COURT OF INDIA
Counsel appearing for the parties :
Senior Advocates :
F. S. Nariman, Rafiq Dada and V. A. Bobde.
Other advocates :
Bhavesh Panjwani, H. V. Shankar, P. Sancheti, Sameer Parekh, T. N. Subramanian,
S. Wajifdar, Lalit Chauhan, P. H. Parekh, Beloslay Kumar Rajesh, B. B.
Singh, D. M. Popat, J. S. Goswami, Ms. Vanita Bhargava, Ms. Bina Gupta
and Sanjay Kapur.
JUDGMENT
The judgment of the court was delivered by
S. SAGHIR AHMAD J. - Leave granted in both the special leave petitions.
Hindustan Construction Company Limited (for short, "HCCL") was awarded
a contract for the construction of Icha Dam across the river Kharkai in
village Kuju by the State of Bihar (for short, "the defendants"). The
contract was awarded in the sum of Rs. 39,71,31,019 on April 25, 1989.
The period of contract was 42 months and the work was to be completed
by October 24, 1992. In terms of the agreement, HCCL was required to furnish,
and it did furnish, a bank guarantee for 10 per cent. of the contract
price as "performance guarantee" in the sum of rupees three crores ninety-seven
lakhs thirteen thousand one hundred and two only. Another bank guarantee
which was required to be furnished by HCCL, and which it did furnish,
was the guarantee against "mobilisation advance" which was to be provided
by the defendants from time to time to the HCCL during the course of the
contract. HCCL has already furnished fifty "mobilisation advance" bank
guarantees aggregating in all to Rs. 532 lakhs. In addition to these bank
guarantees, HCCL had also furnished another "mobilisation advance" bank
guarantee dated July 2, 1991, for Rs. 40 lakhs, for which no advance has
been paid by the State of Bihar. This bank guarantee is, however, not
in question in these proceedings.
Both the bank guarantees were invoked by the defendants and it was, at
this stage, that HCCL filed a suit on October 21, 1992, in the Bombay
High Court against State Bank of India, State Bank of Patiala and Indian
Bank (defendants Nos. 1 to 3) and the State of Bihar and its officers
(defendants Nos. 4 to 6) for various reliefs, including the principal
relief that defendants Nos. 1 to 3 may be restrained from making payment
of the amount covered by the aforesaid bank guarantees to defendants Nos.
4 to 6. An interim order was passed by the single judge in the suit on
October 27, 1992, and under this interim order, the defendants were restrained
from invoking the bank guarantees and the banks were restrained from making
payment of the amount covered by the bank guarantees to the defendants.
The interim order was confirmed on February 9, 1996.
Defendants Nos. 4 to 6, who contested the suit, pleaded, inter alia, that
HCCL had not adhered to the schedule of work and had rather abandoned
the work after it had received the "mobilisation advance" and it was for
this reason that both the bank guarantees were invoked.
The order passed by the single judge was challenged in appeal by the defendants
before the Division Bench and the Division Bench, by the impugned judgment
dated March 20, 1998, vacated the injunction order in respect of the bank
guarantee relating to "mobilisation advance", but the injunction order
in respect of the "performance guarantee" was maintained.
F. S. Nariman, senior advocate, appearing on behalf of HCCL has assailed
the order of the Division Bench of the Bombay High Court on various grounds,
including the ground that invocation of the bank guarantee relating to
"mobilisation advance" was wholly illegal and the High Court was wrong
in vacating the injunction order relating to that guarantee. It is contended
that this bank guarantee could be invoked only if the amount lent to HCCL
as "mobilisation advance" had become payable in terms of clause 9 of the
principal contract which was specifically referred to in the bank guarantee
and since the conditions contemplated by clause 9 did not exist, the invocation
itself was bad. The single judge, it is contended, was right in granting
the injunction order which should not have been disturbed by the Division
Bench.
The defendants have filed a separate appeal against that part of the order
by which the injunction order in respect of the "performance guarantee"
has been upheld by the Division Bench. It is contended on their behalf
that the "performance guarantee", which constituted a separate and distinct
contract between the defendants and the bank, was unconditional and unequivocal
and since the bank had undertaken to pay the amount covered by that guarantee
to the defendants on their demand, the injunction order, granted by the
High Court, was liable to be set aside.
Now, a bank guarantee is the common mode of securing payment of money
in commercial dealings as the beneficiary, under the guarantee, is entitled
to realise the whole of the amount under that guarantee in terms thereof
irrespective of any pending dispute between the person on whose behalf
the guarantee was given and the beneficiary. In contracts awarded to private
individuals by the Government, which involve huge expenditure, as, for
example, construction contracts, bank guarantees are usually required
to be furnished in favour of the Government to secure payments made to
the contractor as "advance" from time to time during the course of the
contract as also to secure performance of the work entrusted under the
contract. Such guarantees are encashable in terms thereof on the lapse
of the contractor either in the performance of the work or in paying back
to the "Government advance", the guarantee is invoked and the amount is
recovered from the bank. It is for this reason that the courts are reluctant
in granting an injunction against the invocation of a bank guarantee,
except in the case of fraud, which should be an established fraud, or
where irretrievable injury was likely to be caused to the guarantor. This
was the principle laid down by this court in various decisions. In U.
P. Co-operative Federation Ltd. v. Singh Consultants and Engineers (P.)
Ltd. [1988] 1 SCC 174; [1989] 65 Comp Cas 283, the law laid down in Bolivinter
Oil SA v. Chase Manhattan Bank [1984] 1 All ER 351 (CA) was approved and
it was held that an unconditional bank guarantee could be invoked in terms
thereof by the person in whose favour the bank guarantee was given and
the courts would not grant any injunction restraining the invocation except
in the case of fraud or irretrievable injury. In Svenska Handelsbanken
v. Indian Charge Chrome [1994] 79 Comp Cas 589; [1994] 1 SCC 502, Larsen
and Toubro Ltd. v. Maharashtra State Electricity Board [1995] 6 SCC 68;
[1996] 85 Comp Cas 214, Hindustan Steel Works Construction Ltd. v. G.
S. Atwal and Co. (Engineers) Pvt. Ltd. [1995] 6 SCC 76; [1996] 85 Comp
Cas 270, National Thermal Power Corporation Ltd. v. Flowmore (P.) Ltd.
[1995] 84 Comp Cas 97; [1995] 4 SCC 515, State of Maharashtra v. National
Construction Co. [1996] 1 SCC 735; [1998] 92 Comp Cas 21 and Hindustan
Steelworks Construction Ltd. v. Tarapore and Co. [1996] 87 Comp Cas 344;
[1996] 5 SCC 34 as also in U.P. State Sugar Corporation v. Sumac International
Ltd. [1997] 89 Comp Cas 179; [1997] 1 SCC 568, the same principle has
been laid down and reiterated.
What is important, therefore, is that the bank guarantee should be in
unequivocal terms, unconditional and recite that the amount would be paid
without demur or objection and irrespective of any dispute that might
have cropped up or might have been pending between the beneficiary under
the bank guarantee and the person on whose behalf the guarantee was furnished.
The terms of the bank guarantees are, therefore, extremely material. Since
the bank guarantee represents an independent contract between the bank
and the beneficiary, both the parties would be bound by the terms thereof.
The invocation, therefore, will have to be in accordance with the terms
of the bank guarantee; or else, the invocation itself would be bad.
In the instant case, the whole matter can be disposed of purely on the
basis of the terms of the bank guarantee.
We will first consider the bank guarantee relating to "mobilisation advance".
This guarantee was furnished in terms of clause 9 of the principal contract
between the HCCL and the defendants which provides as under :
"9. Advance Mobilisation Loan. - The employer will make an advance loan
to the contractor at 13 per cent. simple interest per annum for the costs
of mobilisation in respect of the works in a lump sum amount equivalent
up to 15 per cent. of the contract price named in the letter of acceptance,
payable in the proportionate amounts of foreign and local currencies as
provided for in the contract. Payment of the loan will be due under separate
certification by the engineer after (i) execution of the form of agreement
by the parties thereto, (ii) provision by the contractor of the performance
security in accordance with clause 5, and (iii) provision by the contractor
of a bank guarantee, by a bank acceptable to the employer in an amount
equal to the advance loan, such bank guarantee to remain effective until
the advance loan has been completely repaid by the contractor out of current
earnings under the contract and certified accordingly by the engineer.
A form of bank guarantee acceptable to the employer is indicated in section
9. Annexure B. The advance loan shall be used by the contractor exclusively
for mobilisation expenditures, including the acquisition of constructional
plant, in connection with the works. Should the contractor misappropriate
any portion of the advance loan, it shall become due and payable immediately,
and no further loan will be made to the contractor thereafter. The advance
mobilisation loan, shall be paid within 15 days of the date of certification."
It was in terms of the above clause that the bank guarantee was furnished
by the HCCL. It provides as under :
"The Executive Engineer,
Kharkai Dam Division II, Icha,
Chaliama, Post Kesargarhia,
Dist. Singhbhum, Bihar.
Ref. : Construction of Icha Dam-Subernarekha Multipurpose Project-Contract/Tender
Notice No. SMP/ICC/CE-8/87, Adityapur, dated 23-10-1987.
In accordance with the provisions of the conditions of contract, clause
9 (advance mobilisation loan) of the abovementioned contract, the Hindustan
Construction Co. Ltd., incorporated in Bombay, under the Companies Act,
1956, and having their registered office at construction house, Walchand
Hirachand Marg, Ballard Estate, Bombay-400 038 (hereinafter called 'the
contractor') shall deposit with the Executive Engineer, Kharkai Dam Division
II, Icha, Chaliama, Post Kesargarhia, District Singhbhum, Bihar, a bank
guarantee to guarantee their proper and faithful performance under the
said clause of the contract in an amount of Rs. 10,00,000 (rupees ten
lakhs only).
We, the State Bank of India, incorporated under the State Bank of India
Act, 1955, and having one of our branches at Nyayamurti C. N. Vaidya Marg,
Fort, Bombay-400 023 (hereinafter referred to as 'the said bank'), as
instructed by the contractor, agree unconditionally and irrevocably to
guarantee as primary obligator and not as surety merely, the payment of
the Executive Engineer, Kharkai Dam Division II, Icha, Chaliama, Post
Kesargarhia, District Singhbhum, Bihar, on his first demand without whatsoever
right of objection on our part and without his first claim to the contractor,
in the amount not exceeding Rs. 10,00,000 (rupees ten lakhs only) in the
event that the obligations expressed in the said clause of the abovementioned
contract have not been fulfilled by the contractor giving the right of
claim to the employer for recovery of the whole or part of the advance
mobilisation loan from the contractor under the contract.
We further agree that no change or addition to or other modification of
the terms of the contract or of works to be performed thereunder or of
any of the contract documents which may be made between the Executive
Engineer, Kharkai Dam Division II, Icha, Chaliama, Post Kesargarhia, District
Singhbhum, Bihar, and the contractor, shall in any way release us from
any liability under this guarantee, and we hereby waive notice of any
such change, addition or modification.
Our liability under this guarantee is restricted to an amount not exceeding
Rs. 10,00,000 (rupees ten lakhs only) and the said guarantee shall remain
in full force up to 11th October, 1990, with a claim period of six months
thereafter, i.e., up to 11th April, 1991, twelve months after the issuing
of maintenance certificate, whichever is earlier. Unless demand or claim
under this guarantee is made on us in writing on or before 11th April,
1991, we shall be relieved and discharged from all liabilities thereafter.
This guarantee shall remain valid and in full effect from the date of
the advance payment under the contract until the Executive Engineer, Kharkai
Dam Division II, Icha, Chaliama, Post Kesargarhia, District Singhbhum,
Bihar, receives full repayment of the same amount from the contractor,
but not later than 11th April, 1991, any case.
Dated at Bombay this 12th October, 1989.
For State Bank of India,
(Sd.) ...............
Manager,
Commercial Branch,
Bombay 400 023."
The bank, in the above guarantee, no doubt, has used the expression "agree
unconditionally and irrevocably" to guarantee payment to the Executive
Engineer on his first demand without any right of objection, but these
expressions are immediately qualified by the following :
". . . in the event that the obligations expressed in the said clause
of the abovementioned contract have not been fulfilled by the contractor
giving the right of claim to the employer for recovery of the whole or
part of the advance mobilisation loan from the contractor under the contract."
This condition clearly refers to the original contract between the HCCL
and the defendants and postulates that if the obligations, expressed in
the contract, are not fulfilled by the HCCL giving to the defendants the
right to claim recovery of the whole or part of the "advance mobilisation
loan", then the bank would pay the amount due under the guarantee to the
Executive Engineer. By referring specifically to clause 9, the bank has
qualified its liability to pay the amount covered by the guarantee relating
to "advance mobilisation loan" to the Executive Engineer only if the obligations
under the contract were not fulfilled by HCCL or the HCCL has mis-appropriated
any portion of the "advance mobilisation loan". It is in these circumstances
that the aforesaid clause would operate and the whole of the amount covered
by the "mobilisation advance" would become payable on demand. The bank
guarantee thus could be invoked only in the circumstances referred to
in clause 9 whereunder the amount, would become payable only if the obligations
are not fulfilled or there is misappropriation, That being so, the bank
guarantee could not be said to be unconditional or unequivocal in terms
so that the defendants could be said to have had an unfettered right to
invoke that guarantee and demand immediate payment thereof from the bank.
This aspect of the matter was wholly ignored by the High Court and it
unnecessarily interfered with the order of injunction, granted by the
single judge, by which the defendants were restrained from invoking the
bank guarantee.
Coming to the other appeal which has been filed by the defendants in respect
of "performance guarantee", it may be stated that the single judge as
also the Division Bench of the High Court have maintained the injunction
order and restrained the defendants from invoking the guarantee. The banks
have also been restrained from making payment of the amount stipulated
by the "performance guarantee" to the defendants.
The "performance guarantee" was furnished in terms of clause 5 of the
agreement which provides as under :
"(a) For the due performance of the contract, the tender shall contain
an undertaking by the contractor to obtain when required a bond or guarantee
of an insurance company or bank, or other approved sureties to be jointly
and severally bound with the contractor to the employer, in a sum not
exceeding that stated in the letter of acceptance for such bond or guarantee,
the said insurance company or bank sureties and the terms of the said
bond or guarantee shall be such as shall be approved by the employer.
The obtaining of such bond or guarantee or the provisions of such sureties
and the cost of the bond or guarantee to be so entered into shall be at
the expense in all respects of the contractors unless the contract otherwise
provides.
(b) The performance security shall be submitted by the contractor within
30 days of issue of the letter of acceptance and shall be in the form
of a bank guarantee or a bond (at the contractor's option). The amount
of the bank guarantee shall be 10 (ten) per cent. of the contract price,
or the amount of the bond provided by insurance or bonding company shall
be 30 (thirty) per cent. of the contract price. If the performance security
is in the form of a bank guarantee, it shall be issued either (i) by a
local bank or a foreign bank through a correspondent local bank, or (ii)
directly by a foreign bank acceptable to the employer. The performance
security shall be denominated in the types and proportions of currencies
in which the contract price is payable. The performance security will
be released by the employer not later than 30 days following the date
of delivery of the certificate of completion of works by the engineer."
The "performance guarantee" is in the following terms :
"The Chief Engineer,
Subernarekha Multipurpose Project,
Icha Galudih Complex,
Adityapur, Jamshedpur,
Bihar.
Whereas
The Hindustan Construction Company Limited, incorporated in Bombay, under
the Companies Act, 1956, and having their registered office at Construction
House, Walchand Hirachand Marg, Ballard Estate, Bombay-400 038 (hereinafter
called 'the contractor') has undertaken, in pursuance of contract/Tender
Notice No. SMP/IGC/CE-8/87, Adityapur, dated 23-10-1987, to execute the
work of construction of Icha Dam, Subernarekha Multipurpose Project (hereinafter
called 'the contract').
And whereas it has been stipulated by you in the said contract that the
contractor shall furnish you with a bank guarantee by a recognised bank
for the sum specified therein as security for compliance with his obligations
in accordance with the contract.
And whereas we, State Bank of India, incorporated under the State Bank
of India Act, 1955, and having our commercial branches at Nyayamurthi
G. N. Vaidya Marg, Bombay 400 023 (hereinafter referred to as the 'bank')
have agreed to give the contractor such a bank guarantee.
Now therefore we, State Bank of India, hereby affirm that we are the guarantor
and responsible to you, on behalf of the contractor up to a total of Rs.
3,97,13,102 (rupees three crores ninety-seven lakhs thirteen thousand
one hundred and two only) such sum being payable in the types and proportions
of currencies in which the contract price is payable and we undertake
to, pay you, upon your first written demand and without cavil or argument,
any sum or sums within the limits of Rs. 3,97,13,102 (rupees three crores
ninety-seven lakhs thirteen thousand one hundred and two only) as aforesaid
without your needing to prove or to show grounds or reasons for your demand
for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the
contractor before presenting us with the demand.
We further agree that no change or addition to or other modification of
the terms of the contract or the works to be performed thereunder or of
any of the contract documents which may be made between you and the contractor
shall in any way release us, from any liability under this guarantee,
and we hereby waive notice of any such change, addition or modification.
Our liability under this guarantee is restricted to an amount not exceeding
Rs. 3,97,13,102 (rupees three crores ninety-seven lakhs thirteen thousand
one hundred and two only) and the guarantee shall remain in force up to
16th October, 1992, with a claim period of one year thereafter, i.e.,
up to 16th October, 1993, or twelve months after the issuing of maintenance
certificate. Unless a demand or claim under the guarantee is made on us
in writing on or before 16th October, 1993, we shall be relieved and discharged
from all our obligations thereafter.
Dated this 17th day of April, 1989.
For State Bank of India,
(Sd.) .............
Manager (Credit),
Commercial Branch,
Bombay 400 023.
Seal
Dated 17th April, 1989."
This guarantee has been furnished to the Chief Engineer but was invoked
by the Executive Engineer by a letter addressed to the branch manager
of the State Bank of India, Commercial Branch, Bombay, reading as under
:
"The Branch Manager,
State Bank of India,
Commercial Branch,
Bombay.
Sub. : Claim against the Bank Guarantee No. A/89/228 dated 17-4-1989,
for Rs. 3,97,13,102 (rupees three crores ninety-seven lakhs thirteen thousand
one hundred and two only) issued in favour of the Hindustan Construction
Company Limited W. H. Marg, Bombay, for earnest money of construction
of Icha Main Dam.
Dear Sir,
A sum of Rs. 3,97,13,102 (rupees three crores ninety-seven lakhs thirteen
thousand one hundred and two only) was granted to the Hindustan Construction
Company Limited, W. H. Marg, Bombay, against the Bank Guarantee No. A/89/228
dated 17-4-1989, the said bank guarantee is valid up to 16-10-1992, only.
Its period of validity has not been extended as yet and no amount against
the said earnest money has been paid by the contractor.
You are, therefore, requested that the bank draft for Rs. 3,97,13,102
(rupees three crores ninety-seven lakhs thirteen thousand one hundred
and two only) drawn in favour of the Executive Engineer, Kharkai Dam Division
No. 2, Icha Chaliama, P. O. Kposherhariha, District West Singhbhum, Chaibasa
payable at State Bank of India, Chaibasa, may kindly be sent to the undersigned
immediately as a claim against the said bank guarantee.
An early action in this matter is solicited.
Yours
faithfully,
(Sd.) Executive
Engineer,
Kharkai Dam Division
No. 2,
Icha-Chaliama."
It is contended by Mr. Nariman that the "performance guarantee" constituted
an independent contract between the bank and the Chief Engineer. The guarantee
was furnished by the bank to the Chief Engineer and, therefore, it could
be invoked only by the Chief Engineer and not by the Executive Engineer.
Learned counsel appearing on behalf of the defendants has contended that
in the general conditions of contract appended to the agreement between
the HCCL and the State of Bihar, the word 'employer" has been defined
to mean the Governor of Bihar acting through the Chief Engineer or his
authorised representatives. The word 'Engineer Incharge" or "Engineer"
has been defined separately to mean Superintending Engineer or the Engineer
appointed from time to time by the "employer" and notified in writing
to the contractor to act as Engineer. It is contended that Executive Engineer
who has invoked the guarantee would be covered not only by the definition
of "employer" but also by the definition of "Engineer Incharge" or "Engineer"
as set out in the general conditions of contract. We are not prepared
to accept this contention.
As pointed out above, a bank guarantee constitutes a separate, distinct
and independent contract. This contract is between the bank and the defendants.
It is independent of the main contract between the HCCL and the defendants.
Since the bank guarantee was furnished to the Chief Engineer and there
is no definition of "Chief Engineer" in the bank guarantee nor is it provided
therein that "Chief Engineer" would also include Executive Engineer, the
bank guarantee could be invoked by none except the Chief Engineer. The
invocation was thus wholly wrong and the bank was under no obligation
to pay the amount covered by the "performance guarantee" to the Executive
Engineer.
We have scrutinised the facts pleaded by the parties in respect of both
the bank guarantees as also the documents filed before us and we are,
prima facie, of the opinion that the lapse was on the part of the defendants
who were not possessed of sufficient funds for completion of the work.
The allegation of the defendants that HCCL itself had abandoned the work
does not, prima facie, appear to be correct and it is for this reason
that we are of the positive view that the "special equities" are wholly
in favour of HCCL.
For the reasons stated above, the appeal arising out of SLP(C) No. 6985
of 1998 is allowed. The judgment and order passed by the Division Bench
of the Bombay High Court in so far as it purports to vacate the injunction
order, granted by the single judge in respect of "performance guarantee",
is set aside and the injunction order granted by the single judge in respect
of both the guarantees, namely, "mobilisation advance" and "performance
guarantee" is maintained. The appeal arising out of SLP(C) No. 12143 of
1998 is dismissed. There shall be no order as to costs.
|