|
BEFORE THE APPELLATE AUTHORITY FOR INDUSTRIAL & FINANCIAL RECONSTRUCTION,
NEW DELHI
RAKESH DWIVEDI, Senior Advocate, AJAY K. JAIN, Advocate, AMARJIT SINGH,
Chief Financial Advisor, for the appellant.
VIVEK SIBAL, Advocate, B. P. GUHA THAKUR, A/R, for Somany Pilkingtons
Ltd.
ORDER
(Date of hearing : 13.8.1999.)
This is an appeal against BIFR's order, dated 3.5.99 in case No. 179/89
holding that M/s. Asiatic Oxygen Ltd. (AOL) was no longer a sick industrial
company and was discharged from the purview of the Sick Industrial Companies
(Special Provisions) Act, 1985 (for short, SICA) vide BIFR's order dated
28.2.97 as its networth had become positive, and that M/s. Somany Pilkingtons
Ltd. (SPL) was free to seek appropriate legal remedy from the competent
court and there was no bar to SPL filing suit or pursuing their cases
in the competent courts.
2. The impugned order was passed on an application, dated 7.1.99 submitted
by SPL to BIFR praying for permission under section
22(1) of SICA to continue with the proceedings in Suit No. 666/89
before the Hon'ble High Court at Calcutta (suit filed by SPL for the recovery
of lease rentals and possession of 17,977 gas cylinders from AOL) and
for restraining AOL/Promoter from disposing of AOL's assets and properties
in violation of the terms of the scheme sanctioned by BIFR for the rehabilitation
of AOL. The hearing was scheduled by BIFR on 3.5.1999 at 11.00 a.m. Notice
of hearing was issued to AOL and M/s. Sibal and Eradi, Advocates and Solicitors.
The notice of hearing mentioned the Case No. 79/89 (Correct No. is 179/89).
It did not mention the purpose of hearing. The notice did not include
any mention of SPL's application, dated 7.1.1999. A copy of SPL's application
was not sent by BIFR to AOL. SPL also did not send a copy of its application,
dated 7.1.1999 to AOL. The address of M/s. Sibal and Eradi, Advocates
and Solicitors, did not show the name of the party whom they represented.
There was no way of AOL knowing the purpose of the hearing scheduled on
3.5.1999. AOL wrote a letter, dated 27.4.1999 to BIFR, stating, inter
alia, that BIFR had by order, dated 28.2.1997 closed the proceedings in
AOL's case, that M/s. Sibal and Eradi, Advocates, had not represented
any party during the hearing of AOL's case by BIFR at any point of time,
that the reason for fixing the hearing was not mentioned in BIFR's notice,
and that, therefore, the hearing was kept in abeyance until the matter
was clarified. Nobody represented AOL at the hearing before BIFR on 3.5.99
when the impugned order was passed. As there was no proper notice of hearing
to AOL, there was denial of natural justice to AOL. We were, therefore,
inclined to remand the matter to BIFR for fresh consideration after hearing
AOL. However, as the subject matter of hearing before BIFR was SPL's prayer
that section 22(1)
of SICA for permission to it continue the proceedings in Suit No. 666/89
against AOL before Hon'ble Calcutta High Court, and as permission under
section 22(1) of
SICA can be sought direct from this Authority during the pendency of an
appeal, and as the counsel for both AOL and SPL wanted the case to be
heard and decided by this Authority on merits instead of being remanded
to BIFR, we heard the appeal on merits.
3. AOL's reference under section
15(1) of SICA was registered as case No. 179/89 by BIFR. On 4.6.90,
BIFR declared AOL to be a sick industrial company within the meaning of
section 3(1)(o)
of SICA and appointed ICICI as operating agency (OA) under section
17(3) of SICA. After several hearings, on 8.10.93, BIFR sanctioned
a scheme for the rehabilitation of AOL under section
18(4) read with it section
19(3) of SICA. Substantial reliefs and sacrifices were extended by
secured creditors to facilitate the rehabilitation of AOL. Taking note
of AOL's annual report for the financial year ended on 31.3.96 and the
fact that AOL's networth had turned positive as on 31.3.1996, BIFR passed
an order, dated 28.2.97 holding that AOL ceased to be a sick industrial
company within the meaning of section
3(1)(o) of SICA, that its case no longer required to be dealt with
by BIFR, that the proceedings in the case were, therefore, closed, but
the obligations/responsibilities, if any, yet to be fulfilled by AOL shall
remain in force, and it would be bound to fulfil the same as per the various
covenants of the scheme sanctioned for its rehabilitation.
4. SPL had filed a suit (Civil Suit No. 666/89) before Hon'ble Calcutta
High Court against AOL for recovery of possession of 17,977 gas cylinders
and recovery of lease rental dues amounting to Rs. 213.70 lakhs along
with interest from 17.8.89 and interest on judgment. The trial court held
that SPL could proceed with the suit for recovery of its property, but
the proceedings for the recovery of money would stand stayed. In SPL's
appeal 363/96 against the trial court's order, the Division Bench of the
Hon'ble Calcutta High Court examined at length the scope of section
22(1) of SICA while taking note of BIFR's order, dated 28.2.1997 and,
by order, dated 4.8.1998, upheld the trial court's order and dismissed
the appeal. The Hon'ble Calcutta High Court held that the scheme sanctioned
by BIFR on 8.10.1993 is still under implementation and, therefore, the
statutory bar under section
22(1) of SICA continues to it be applicable. SPL's SLP (Civil) No.
19181/98 before the Hon'ble Supreme Court of India against the order,
dated 4.8.1998 of the Division Bench of Hon'ble Calcutta High Court in
appeal No. 363/96 was dismissed by the Hon'ble Supreme Court on 16.12.98.
5. The implication of BIFR's jurisdiction in a case, in which a sick industrial
company's net worth has exceeded its accumulated losses, but the sanctioned
scheme has not been fully implemented, were dealt with by this Authority
in some detail in this Authority's order, dated 9.7.96 in appeal 77/96
(M/s. Swan Mills Ltd. Kamgar Kapada Udyog Sahkari Society Ltd. v. BIFR
and others). So long as the scheme is under implementation, BIFR has to
exercise its jurisdiction under various sub-sections [particularly, sub-sections
(5), (9) and (12)] of section
18 of SICA, notwithstanding the fact that the net worth has exceeded
the accumulated losses. It is seen from the cash flow statement of the
sanctioned scheme, dated 8.10.93 for AOL that repayments of certain dues
(payment of deferred interest to financial institutions/banks, sales tax
arrears, funded interest, etc.) have been scheduled upto the year 2002-03.
BIFR cannot refuse to exercise its jurisdiction to ensure that such terms
of the sanctioned scheme are fulfilled and give appropriate directions
in case of any difficulties and consider proposals, if any, for review
and modification in the sanctioned scheme. Had the sanctioned scheme been
fully or substantially implemented, it would have been competent for BIFR
to declared AOL as being outside the purview of SICA by declaring the
scheme as fully implemented or terminated. So long as the scheme continues
to be under implementation, jurisdiction of BIFR can be invoked and, in
that view of the matter, BIFR's order, dated 28.2.1997 cannot be interpreted
to mean that BIFR can refuse to exercise its jurisdiction, if any, applications
are received for review/modification of the sanctioned scheme or the removal
of any difficulties or for monitoring the implementation of the terms
of the scheme.
6. The impugned order was passed by BIFR on the ground that by their order,
dated 28.2.1997, AOL was discharged from the purview of SICA. This ground,
on which the impugned order was passed, is not tenable in view of this
Authority's order, dated 9.7.1996 in appeal 77/96, referred to above,
and the Hon'ble Calcutta High Court's order, dated 4.8.1998 in appeal
No. 363/96, referred to above. The impugned order that SPL was free to
seek legal remedy and file or pursue its case against AOL in court is,
therefore, not tenable.
7. We have now to consider whether SPL should be granted permission under
section 22(1) of
SICA for continuance of proceedings for the recovery of lease rentals
in its suit 666/89 before Hon'ble Calcutta High Court.
8. The learned counsel for AOL contended : in order to tide over liquidity
crisis during 1985-86, AOL resorted to sale and lease-back of cylinders
and as on 31.3.90 AOL's total lease rental liability was Rs. 396 lakhs
towards six lessors; lease rentals of one party were settled and paid
prior to the sanction of the scheme and payment of lease rentals of Rs.
259 lakhs to 5 parties was provided in the sanctioned scheme; re-schedulement
of payment of lease rentals of Rs. 259 lakhs was to be obtained from leasing
companies as per the terms and conditions considered satisfactory by the
banks/institutions (para 3 G(vi) of the sanctioned scheme); 4 parties
had agreed to re-schedulement as proposed in the scheme, but one party,
i.e., SPL had not agreed and this was pointed out to BIFR at the hearing
on 8.10.93; the re-scheduled lease rental dues of Rs. 259 lakhs pertained
to Bengal and Assam Company Ltd. (Rs. 15 lakhs), Oriental Leasing Co.
Ltd. (Rs. 28 lakhs), Overseas Sanmar (Rs. 25 lakhs), Midwest Leasing Co.
(Rs. 17 lakhs) and SPL (Rs. 174 lakhs); the re-scheduled lease rental
dues of 4 parties have already been paid by AOL but SPL had not accepted
the payment; AOL is willing to pay Rs. 174 lakhs to SPL along with interest
from the dates on which these payments were due under the terms of the
sanctioned scheme; AOL has been revived and SPL is now only trying to
thwart the implementation of the sanctioned scheme by resorting to litigation;
SPL was fully aware of the proceedings before BIFR but, after writing
a letter, dated 16.1.91 to BIFR claiming lease rental of Rs. 3.5 crores,
had never pursued the matter with BIFR and neither responded to the public
notice inviting objections/suggestions to the draft scheme nor attended
any hearing before BIFR to press its claim; the scheme is binding on all
parties, including SPL, in view of section
32(1) and section
18(8) of SICA, and SPL is only entitled to receive Rs. 174 lakhs from
AOL; AOL has disposed of some of its units as per the sanctioned scheme
and is contemplating sale of some other units with the approval of the
concerned banks/financial institutions, whereas SPL is only trying to
thwart the profitable operations of AOL; SPL should accept the payment
of Rs. 174 lakhs from AOL and the appeal be dismissed and the prayer of
SPL for permission under section
22(1) of SICA be rejected.
9. The learned counsel for SPL contended : SPL filed suit 666/89 in Hon'ble
Calcutta High Court for the recovery of cylinders and lease rental arrears
of Rs. 213.70 lakhs from AOL and the dues have by now risen to about Rs.
9 crores; SPL was never informed that the scheme included payment of lease
rentals of Rs. 174 lakhs to itself; the distribution of the lease rentals
provided in the scheme has been given by AOL only at this stage when this
appeal is being heard; the scheme does not provide for any sacrifice or
write off on the part of SPL and, therefore, SPL has no obligation to
make any sacrifice; AOL/promoter are not implementing the scheme properly,
and they have sold AOL's unit at Ranipet as a going concern to Praxair
India (P) Ltd. and have planned to sell all their remaining units also
to Praxair India (P) Ltd. even though the sale of these units is not included
in the sanctioned scheme; in this way, SPL apprehends that its security
will be diluted; clause 3 G(vi) required AOL to obtain re-schedulement
of lease rentals from the various leasing companies but no such re-schedulement
was obtained by AOL from SPL; if SPL's dues were included in the scheme,
AOL had an obligation to make payment to SPL but, despite having sold
some of its industrial units, it has not made any payment to SPL; AOL/promoter
are not implementing the scheme, but only claiming protection under section
22(1) of SICA by pleading that the scheme is under implementation;
the appeal be dismissed or SPL be permitted to continue its suit 666/89
before Hon'ble Calcutta High Court for the recovery of its lease rental
dues from AOL.
10. Our conclusions on the contentions of the learned counsel for AOL
and SPL are given below :
(a) The sanctioned scheme, dated 8.10.93 continues to be under implementation.
Several provisions of the scheme will continue to be implemented upto
the year 2002-2003 unless the implementation thereof is achieved earlier
than due dates. Protection under section
22(1) of SICA continues to be available to AOL during the implementation
of the scheme. BIFR has to exercise its jurisdiction under section
18 and various other provisions of SICA until the scheme is fully
implemented or terminated on account of substantial implementation including
discharge of the financial obligations under the scheme.
(b) SPL has a locus standi insofar as its own interests are concerned.
It cannot assume the role of a monitor of the scheme.
(c) AOL cannot modify the sanctioned scheme on is own. During the period
of implementation of the scheme, if it sells or proposes to sell any industrial
unit(s) in addition to the three industrial units which were sold in accordance
with the terms of the sanctioned scheme, it has to approach BIFR for necessary
modification and comply with BIFR's direction in this regard.
(d) SPL is an unsecured creditor. It is not one of those persons whose
consent is required under section
19(1) and (2) of SICA. The question of rights of unsecured creditors
and repayment of their dues by the sick industrial companies for which
rehabilitation schemes are sanctioned under section
18(4) of SICA has been dealt with by this Authority in several appeals.
In the event of winding Up of a sick industrial company, the sale proceeds
from the disposal of the assets of such company are distributed amongst
secured creditors and workers in proportion to their dues; their dues
are likely to be fully realised; unsecured creditors and shareholders
are unlikely to get anything at all. In rehabilitation schemes for sick
industrial companies under the provisions of SICA, financial institutions/banks
and Central/State Governments often extend reliefs and sacrifices; unsecured
creditors cannot expect to receive payment of their dues and interest.
However, if a sick industrial company has large surplus assets, which
are not required for its manufacturing activity and can, therefore, be
sold, and the sale proceeds are expected to be not less than the financial
obligations of such company, then payments can be provided to creditors
without sacrifices by them. On the other hand, if a sick industrial company
is revived through a rehabilitation scheme approved by BIFR, envisaging
reliefs and sacrifices and financial accommodation by financial institutions/banks
and Central/State Governments as well as induction of fresh funds by the
promoters, then the unsecured creditors cannot expect to derive benefit
from such post-scheme prosperity of the company to which they have not
made any contribution. Therefore, the provision made for the payment of
the dues of unsecured creditors in any scheme for a sick industrial company
under section 18(4)
of the Act has to be considered as a provision for full and final settlement
of their pre-scheme dues. It is open to them to make their submissions
before BIFR by responding to public notice of draft rehabilitation scheme
so that their claims are given appropriate consideration by the operating
agency and BIFR. Any other approach to the pre-scheme dues of unsecured
creditors would, in our view, be inconsistent with section
2 of SICA whereby a declaration is made that SICA is for giving effect
to the policy of the State towards securing the principles specified in
clauses (b) and (c) of Article 39 of the Constitution.
11. In the present case, nothing has been brought to our notice by SPL,
nor is there anything in the record before us, to suggest that prior to
the sanction of the scheme on 8.10.93 by BIFR, AOL had surplus assets,
not required for its manufacturing activities, which could be sold and
the sale proceeds therefrom could meet all the financial obligations of
AOL towards its creditors, statutory authorities and workers. After writing
a letter, dated 16.1.99 to BIFR, SPL did not appear before BIFR to make
its submissions regarding its dues. It was open to SPL to pursue its case
with the OA and BIFR, respond to the public notice of draft rehabilitation
scheme and attend the hearing before BIFR after obtaining a copy of the
draft scheme, and press its claims. Even after the sanction of the scheme
by BIFR, SPL could have sought redressal of its grievance by preferring
an appeal under section
25 of SICA. It is, therefore, obvious that SPL had, by its conduct,
acquiesced in the scheme sanctioned by BIFR on 8.10.93. Clause 3 G(iv)
of the scheme stipulates that re-schedulement of lease rentals is to be
obtained from the leasing companies according to the terms satisfactory
to financial institutions/banks. It does not require consent of leasing
companies. It only requires satisfaction of financial institutions/banks.
It does not require consent of leasing companies. It only requires satisfaction
of financial institutions/banks. As the scheme was sanctioned with the
consent of financial institutions/banks, and as SPL did not resort to
legal remedies against the sanctioned scheme, it cannot now challenge
that scheme. Therefore, whatever provision is made in the sanctioned scheme
for the payment of pre-scheme lease rentals due to SPL by AOL, that has
to be treated as full and final settlement of the, pre-scheme lease rental
dues. The terms of the sanctioned scheme have the overriding effect over
other laws by virtue of section
32(1) of SICA and are binding on all shareholders, creditors, guarantors
and employees by virtue of section
18(8) of SICA. It is not necessary to make any specific provision
for sacrifice or write off on behalf of unsecured creditors, because no
consent of unsecured creditors is required under section
19 of SICA. We have no reason to doubt that a provision for payment
of Rs. 174 lakhs in instalments to SPL over the period 1992-1998 is included
in the total provision of Rs. 259 lakhs payable to leasing companies during
that period.
12. AOL's case is that SPL refused to accept the payment of Rs. 174 lakhs
in instalments provided in the sanctioned scheme and withdraw its suit
in Hon'ble Calcutta High Court. SPL's case is that AOL never made or offered
any payment. Instead of going into this controversy, we consider it appropriate
that AOL should now pay this amount of Rs. 174 lakhs to SPL along with
simple interest at 12% per annum, in full and final settlement of the
pre-scheme lease rental dues of SPL, upto the date of payment. In order
to avoid further disputes about the quantum and due dates of instalments
of Rs. 174 lakhs, we have worked these out as follows : Rs. 10.08 lakhs
(31.3.92); Rs. 20.15 lakhs (31.3.93); Rs. 28.22 lakhs (31.3.94); Rs. 28.89
lakhs (31.3.95); Rs. 28.89 lakhs (31.3.96); Rs. 28.89 lakhs (31.3.97);
Rs. 28.88 lakhs (31.3.98). These amounts are to be paid with 12% interest
upto the date of payment by way of one lump sum payment. Both AOL and
SPL to submit statements in suit 666/89 before Hon'ble Calcutta High Court
for a consent decree as stated above. Permission is granted to SPL for
the recovery of the amount calculated as above in full and final settlement
of its pre-scheme lease rentals due from AOL. BIFR's order stands modified
accordingly. The appeal stands disposed of.
|