|
JUDGMENT
V. S. AGGARWAL, J. - Petitioner M/s. Oswal Spinning and Weaving Mills
Ltd. is a public limited company. It had one alloy steel unit with three
numbers of induction furnaces. The petitioner company was approached by
respondent M/s. Kansal Alloys, Proprietor, Kansal Fibre Limited, to sell
the complete alloy steel unit comprising of two acres of land and building
situated thereupon alongwith one induction furnace of three metric ton
and two induction furnaces of one metric ton each as well as all accessories,
etc., situated at Ludhiana. The sale consideration was settled at Rs.
1.35 crores only. An agreement to that effect had been entered into between
the parties on 14.2.1996. The respondent company paid the entire sale
consideration except Rs. 15 lakhs. The said amount was agreed to be paid
on actual transfer of power connection with contract demand and load in
its favour. Accordingly, the alloy steel unit was transferred to respondent
company which started operating the plant. It was agreed that till the
connection is transferred in favour of the respondent company, it shall
continue to use electricity from the combined power connection of the
petitioner company and would pay the electricity consumption charges on
monthly basis. The said system continued and the petitioner company used
to send the detailed calculation for making payment. Upto September, 1998,
payments were made except Rs. 3,60,809 which was due to the petitioner
company. However, the bill for the energy consumed in the month of October,
1998, was received from the Punjab State Electricity Board. On receipt
of the bill, petitioner company after getting the acknowledgement raised
a debit note for making payment of Rs. 20,36,224. The consumption of the
details were provided to the respondent company. No payment was made by
the respondent company. The petitioner company became liable to pay surcharge
at the rate of 10% on the unpaid amount. Even bill for November, 1998,
was received. It was for Rs. 21,21,965 and the share of the respondent
company comes to Rs. 12,82,221. Even the same had not been paid. In this
process, a sum of Rs.40,71,838 were due from the respondent company. A
notice had been served for payment of the debt. No reply was received.
Hence, an application had been filed for winding up of the respondent
company under the provisions of section
439 read section 56
with section 433 and
section 434 of the
Companies Act, 1956 (for short 'the Act').
2. The respondents contested the petition. As per respondents, the claim
of the petitioner company is false and the amount claimed is not due. The
defence offered was that consideration money was paid because of the attraction
of electricity connection which was in existence at the premises, i.e.,
LS-49 bearing 3070 K.W. after the same had been reduced by 1400 K.W. by
the petitioner company. The respondent company had further incurred an expenditure
of about Rs. 50 lakhs approximately to make the unit functional. It was
agreed by the petitioner company that the electricity connection shall be
transferred in the name of the respondent company and all expenditure which
was to be incurred for the said purpose was to be incurred by the petitioner
company. The said electricity connection has never been transferred. To
the contrary, the said electricity connection alongwith LS-49 was got merged
into LS-5. The respondent company even made a request that the electricity
connection be shifted to its premises. The electricity connection has not
been segregated. In this process, the petitioner company misled the respondent
company and on that basis, took Rs. 120 lakhs from the respondent company.
3. It was not disputed that it had been agreed that a sub-meter shall be
installed at the premises of the petitioner company and that whatever electricity
would be consumed by the petitioner company, the consumption would be deducted
from the total bill of the connection. The electricity was to be shared
in the ratio of 17:13. The petitioner company had been taking advantage
of the general consumption of the electricity to the extent of 1700 K.W.
During the period when the petitioner company was not utilising 1370 K.W.
of electricity, the petitioner company had taken the advantage and Rs. 52,45,513.90
had been paid by the respondent company for and on behalf of the petitioner
company for which adjustment has also been claimed.
4. On 30.3.1999, this court directed that a senior officer from the Punjab
State Electricity Board, Ludhiana, of the large consumer section well conversant
with the facts of the case should be present to clarify the extent and concept
of minimum charges. On 8.4.1999 an Assistant Engineer of the Punjab State
Electricity Board was present who was not able to answer the questions put
to him. So a Senior Executive Engineer (Operation) was called and the case
was adjourned. It appears that the Electricity Board employees were not
able to answer the question and, therefore, even When the matter was relisted,
no such request was made. The parties in this process were heard.
5. Under section 433
of the Act, a company can be wound up section
56 by the court if it is unable to pay its debts or the court is of
the opinion that it is just and equitable that the company should be wound
up. The other grounds on which a company can be wound up are not relevant
for the disposal of the present petition. What is impressed is that the
respondent company has not been able to pay the debts and the amount as
claimed.
6. It is well known that a winding up petition is an alternative in the
case of a company. The normal procedure otherwise is to recover the amount
in accordance with law. The machinery for winding up is not allowed to be
used for realisation of the debts. This question has been considered by
the Supreme Court in the case of Amalgamated Commercial Traders (P) Ltd.
v. A. C. K. Krishnaswami and another (1965) 35 Comp Cas 456 (SC). The Supreme
Court held that a winding up petition is not a legitimate means of seeking
enforcement of a debt which is bona fide disputed. A petition presented
ostensibly for a winding up order, but really to exercise pressure should
be dismissed; otherwise the said provision can be misutilised. Same view
was expressed by this court in the case of Ambala Bus Syndicate (P) Ltd.
v. Bala Financiers (P) Ltd. (in liquidation) (1984) 2 Comp LJ 372 (P&H)
: (1986) 59 Comp Cas 838 (P&H). This court relied upon a well known
decision of the Supreme Court in the case of Madhusudan Gordhandas and Co.
v. Madhu Woollen Industries (P) Ltd. (1972) 42 Comp Cas 125 (SC). It was
concluded that if there is a bona fide dispute and the defence is substantial,
the court will not wind up the company. Same view prevailed with the Karnataka
High Court in the case of Kamadenu Enterprises v. Vivek Textile Mills (P)
Ltd. (1984) 55 Comp Cas 68 (Karn) and in the case of T. Srinivasa v. Flemming
(India) Apotheke Private Ltd. (1995) 5 Comp LJ 438 (Karn) : (1990) 68 Comp
Cas 506 (Karn).
7. The position in the present case is that at the time when sale transaction
took place, the parties even with respect to electricity had also made a
settlement. The relevant part of that agreement reads as under :
"It has been agreed by the party of the 1st part (M/s. Oswal Spinning &
Weaving Mills Ltd.) that it would get transfer of the power connection lying
installed, in favour of the party of the 2nd part (Kansal Alloys Prop. M/s.
Kansal Fibres Ltd.), at its own cost, and it shall complete all the formalities
necessary for the transfer of the said electricity connection in favour
of the 2nd party. Till the electric connection is actually transferred in
favour of the 2nd part, it would be the responsibility of the 1st part to
install a sub-meter, segregating furnaces load from total load of account
No. LS-49. The party of the 2nd part is bound to make payment to the party
of the 1st part equal of the consumption charges and any other charges such
as meter rent, fuel consumption charges etc. as shown in the monthly electricity
bill of account of LS-49 after deducting the reading shown in sub-meter
installed therein. This payment will be made by the party of the 2nd part
to the party of the 1st part atleast seven days before the last date of
payment of bill by demand draft. It is obligatory on the part of the party
of 1st part to deposit the bill before due date. In case the power bill
is not deposited within due date by the party of the 1st part after getting
due share from the party of the 2nd part, the amount of the surcharge imposed
by PSEB will be paid by the party of the 1st part only. In case the party
of the 2nd part fails to give their due shares to the party of the 1st part,
the surcharge amount will have to be paid by the party of the 2nd part in
toto.
The party of the 2nd part shall adhere strictly to the restrictions imposed
by the Punjab State Electricity Board on this electric connection No. LS-49,
i.e., peak load hours restrictions. In case any of the restrictions are
violated or the party of the 2nd part commits the breach of abridged conditions
of supply including condition No. 33 it shall be responsible for all legal
consequences, both civil as well as criminal. The party of the 2nd part
shall not tamper with any seals of or electrical installation or misuse
the electricity in any way. In case the party of the 2nd part commits the
breach of abridged conditions of supply and commits theft of electricity,
it shall be the responsibility of the party of the 2nd part. The party of
the 2nd part shall be liable to compensate the Board on the part of the
party of the 1st part in case the electric connection is disconnected on
any account or theft or offence committed by the party of the second part.
However, the party of the second part shall be entitled to use the load
permissible to be used during the peak load hours restrictions, the party
of the 1st part shall not share this load."
8. It is not in controversy that till date, the electric meter has not been
transferred in the name of the respondent company. Instead, the electricity
connection was merged into LS-5. Though the petitioner company has placed
on the record the calculation as to how the amount is due, yet the same
has been clarified. Annexure R-1 has been placed on the record as the calculation
by the respondent company showing as to how, in fact, more amount is due
to the respondent company and that what was actually paid by the petitioner
company to the Punjab State Electricity Board was far less. It is thus a
dispute pertaining to the calculation and thereupon an exact figure could
be arrived at as to how much amount is due.
9. In addition to that, the respondent company claimed a set off of a particular
amount. When such is the controversy coupled with the dispute that it is
asserted that there was erratic supply of electricity by the petitioner
company, it would be in the fitness of things that the matter is decided
by an appropriate civil court.
10. In such like disputes, winding up is not necessary because the remedy
provided under section 434
of the Act is section 56
not a matter of right. The discretion, in the peculiar facts, thus cannot
be exercised in favour of winding up of the respondent company.
11. For these reasons, the company petition is dismissed. It is clarified
that nothing said herein is any expression of opinion on the merits of the
matter.
|